Article 12415

Title of the article

USAGE OF THE METHOD OF DISTRIBUTED SPECIFIC POWERS FOR DETERMINATION OF INSTALLATION SITES OF POWER SOURCES IN WORKSHOPS OF MACHINE-BUILDING PLANTS

Authors

Mikhaylov Sergey Alekseevich, chief specialist, Samara branch of OJSC «Moscow unit of energy» (443080, office 404, 70 Revolyutsionnaya street, Samara, Russia), mihailov@gmail.com
Goryachev Vladimir Yakovlevich, doctor of technical sciences, professor, sub-department of electricity and electronics, Penza State University (440026, 40 Krasnaya street, Penza, Russia), gorvlad1@yandex.ru
Brostilova Tat'yana Yur'evna, candidate of technical sciences, associate professor, sub-department of electricity and electronics, Penza State University (440026, 40 Krasnaya street, Penza, Russia), tat-krupkina@yandex.ru

Index UDK

621.311

Abstract

In the article considered the ability to install two substation in the workshop. Is offered to use the method of distribution specific power for determine the optimum installation location of substation. The power losses value and metal consumption is compared for options of one or two substations.

Key words

electricity, substation, optimization, consumer of electricity, electrical energy losses, metal consumption.

Download PDF

 

Дата создания: 05.04.2016 09:20
Дата обновления: 05.04.2016 14:21